Project details

Technical re-equipment of the raw water supply scheme to the ultrafiltration unit (UFU) of the chemical department at the CHP plant

CLIENT
CHP
YEARS OF IMPLEMENTATION
2016—2017
TYPE OF WORKS
Design, equipment supply, installation, software development, commissioning

Equipment used, specifics of works provided

  1. NK GRUNDFOS 37 kW pumps, LDM control valves RV212 DN400, pressure, flow, temperature and level sensors, heating of process pipelines.

Design
Equipment supply
Installation works
Software development
Commissioning works