Technical re-equipment of the raw water supply scheme for the ultrafiltration unit (UFU) at the CHP chemical shop
CLIENT
CHP
YEARS OF IMPLEMENTATION
2016—2017
TYPE OF WORKS
Design, equipment supply, installation, software development, commissioning
Equipment used, specifics of works provided
- A cascade control system to control four 37 kW pumping units with a uniform operating time, as well as a raw water tanks level control system were implemented.
- The layout and assembly of the control cabinets was carried out by the company’s specialists using Siemens and Schneider Electric equipment.
- The system was programmatically integrated into the existing water treatment SCADA (SCADA SIMATIC WinCC).
Design
Equipment supply
Installation works
Software development
Commissioning works
Similar projects
Adjustable micropower drive for coal hoisting machine MPB 5x2x2
Adjustment of project documentation “DZF. Automatic pump control system 8NDV”
Automation of the combustion safety system at the Centralized Processing Plant furnace unit No. 5 of...
Automation of drying at 1, 3, 4 process lines at Centralized processing plant
CHP plant reconstruction with the conversion of boiler units No. 6, No. 7, No. 8 to burn non-designe...
Commissioning of five distribution devices for connecting frequency converters, including parameteri...
Construction of a water treatment plant at PJSC “POEZ-KERNEL GROUP” for the project impl...
Design and commisioning of the control and safety system for the GM-3 hydraulic unit
Emergencies early detection and people notification, in case of emergencies occurrence, system at th...
Implementation of the Coastal Pumping Station (CPS) NDV adjustable electric drive system at the CHP ...
Installation and commissioning of a set of equipment for water purification by reverse osmosis techn...
Modernization and development of electric drives and CNC control systems for metal-cutting and other...
Modernization of the automatic water level in boiler drums No. 1-4 regulation and control system
Modernization of the DZF unified control room
Modernization of the sewage pumping stations SPS-4 and SPS-7
Monitoring of the current load of the mill ball drive electric drives at mill No. 21115, inv. No. 12...
Oxygen and natural gas metering at the BRM based on Ergomera equipment
Reconstruction (technical upgrading) of the control and management system for the turbo-generator
Reconstruction and automation of section No. 12, DSP
Reconstruction of the 16 ATA steam supply scheme
Reconstruction of the CHP plant with the conversion of boiler unit No. 9 to burn non-project fuel (g...
Setting up control systems and a dispatching system for autonomous boiler houses (11 units) in Chern...
Setting-up an automatic frequency control station for electric motors of network pumps with the inst...
Technical re-equipment of the automated control system for pumping units (ACS PU)
Technical re-equipment of the automatic control system (ACS) for the superheated steam temperature c...
Technical re-equipment of the wastewater treatment unit by applying the complex technology of membra...
Got questions?
Want to know more about our products or services? Please, fill in the form, and our Customer Relations Manager will contact you as soon as possible!
Message us 