Technical re-equipment of 0.4 kV electric supply boards. Board of the fecal pumping station of the fuel oil economy FPNS MZH at the CHP plant
CLIENT
CHP
YEARS OF IMPLEMENTATION
2016—2017
TYPE OF WORKS
Design, installation, equipment supply, programming and commissioning
Equipment used, specifics of works provided
- Layout and assembly of a 0.4 kV power switchgear based on the Prisma P design and Schneider Electric equipment.
Design
Installation works
Equipment supply
Commissioning works
Programming works
Similar projects
CSP. Implementation of special automatic load disconnection (SALD)
Installation of repair stations 220/380 V at OPU
Modernization of 0.4 kV PNS-1 distribution devices. TSHH, temporary power supply
Modernization of 0.4 kV switchgear at PNS-1 TSHG
Modernization of the energy saving system at the Pellets Production Workshop (TsVO) ACS line
Overhaul of the existing SPP with the installation of a new 85 kVA diesel generator and installation...
Reconstruction of TP-33-1
Replacement of high-voltage input cells at fifteen different B-110 circuit breakers of the B-110-200...
Replacement of switchgear 0.4 kV of TS 03-1 BRM
Transformer replacement at TP 14-2
Transformer replacement at TP 15-2
Transformer replacement at TP 16-2
Transformer replacement at TP 17-2