Project details

Replacement of the electromagnetic exciter of the turbine generator TV-60-2 and ARZ type POA with a single-group two-channel thyristor self-excitation system implementing redundancy schemes (1+1) with microprocessor-based ARV and AWP for monitoring turbine generators TG-5, TG-6, TG-7

CLIENT
Ltd. “Euro-Rekonstruktsia”
YEARS OF IMPLEMENTATION
2017—2021
TYPE OF WORKS
Design, installation works, equipment supply, software development, complex tests and commissioning works

Equipment used, specifics of works provided

  1. The works starting with dismantling the old system finishing with grid connection to the Ukrainian power system with 60 MW output for TG-5 took 41 days, including dismantling, installation, connection of power and control circuits, as well as comprehensive testing and commissioning.
  2. The excitation system SSTE-800-250-2.5-UHL4 (SPE “PREOFRESHCHATELNAYA TECHNIKA”) is a Ukrainian development, the field damping system is developed under a Ukrainian patent.
  3. The power transformer TSZP-630/10-UZ (PE “ELTIZ”) 630 kVA, 10.5 kV/0.475 kV, U/D-11 and the microprocessor-based relay protection device RZL-01 (LLC “SPE “RELSIS”) are also developed by Ukrainian companies.
  4. The premises with the excitation system equipment were air-conditioned by MIDEA MFM-48 column air conditioners.
  5. As part of the comprehensive testing and commissioning, thermal imaging surveys of the power thyristor sections and process oscillography were performed using the ADC-BS-8V-9C digital recorder of electrical parameters.
  6. Digital models of the turbine generator were used to develop the field damping system and to adjust the current, voltage, and reactive power controllers.

 

Design
Installation works
Equipment supply
Software development
Complex tests
Commissioning works
Got questions?
Want to know more about our products or services? Please, fill in the form, and our Customer Relations Manager will contact you as soon as possible!
Message us

    Send a request

    Right Menu Icon