Reconstruction (technical upgrading) of the control and management system for the turbo-generator
CLIENT
YEARS OF IMPLEMENTATION
2023-2024
TYPE OF WORKS
Installation works, equipment supply, software development
Equipment used, specifics of works provided
Based on the OVATION software and hardware complex from Emerson, the following automated control systems have been implemented:
- for supporting the heating load of the turbine;
- for managing the operation of turbo-generator Unit No. 4 in primary, secondary, and tertiary frequency and power regulation for the energy system, as well as during the operation of emergency protection systems;
- for automatic unloading of the unit and power limitation of the unit;
- for providing self-diagnostics for the control system’s technical means and executed functions;
- for collecting and displaying current signal values (input and output) for the monitored equipment;
- for accumulating and storing all information for future review.
To monitor signs of deviations from normal operating conditions, turbo-generator Unit No. 4 is equipped with the following control points of the technological parameters:
- measurement of active and reactive power of the unit;
- measurement of rotor speed for the electronic safety relay (ESR);
- measurement of rotor speed for the electrical control system (ECS);
- measurement of relative expansions of rotors for CVT, CST, and CNT;
- measurement of thermal expansion of the casing (TEC);
- measurement of rotor distortion (RD);
- measurement of axial rotor displacement (ARD);
- measurement of vibration velocity of bearing housings;
- discrete input signals of the “dry contact” type are routed to the signal input modules for event sequencing in the Ovation control system;
- analog output signals of 4-20 mA are provided as voltage by the Ovation control system.
Installation works
Equipment supply
Software development
Similar projects
Adjustable micropower drive for coal hoisting machine MPB 5x2x2
Adjustment of project documentation “DZF. Automatic pump control system 8NDV”
Automation of drying at 1, 3, 4 process lines at Centralized processing plant
Automation of the combustion safety system at the Centralized Processing Plant furnace unit No. 5 of...
CHP plant reconstruction with the conversion of boiler units No. 6, No. 7, No. 8 to burn non-designe...
Commissioning of five distribution devices for connecting frequency converters, including parameteri...
Construction of a water treatment plant at PJSC “POEZ-KERNEL GROUP” for the project impl...
Emergencies early detection and people notification, in case of emergencies occurrence, system at th...
Implementation of the Coastal Pumping Station (CPS) NDV adjustable electric drive system at the CHP ...
Installation and commissioning of a set of equipment for water purification by reverse osmosis techn...
Design and commisioning of the control and safety system for the GM-3 hydraulic unit
Modernization and development of electric drives and CNC control systems for metal-cutting and other...
Modernization of the automatic water level in boiler drums No. 1-4 regulation and control system
Modernization of the DZF unified control room
Modernization of the sewage pumping stations SPS-4 and SPS-7
Monitoring of the current load of the mill ball drive electric drives at mill No. 21115, inv. No. 12...
Oxygen and natural gas metering at the BRM based on Ergomera equipment
Reconstruction and automation of section No. 12, DSP
Reconstruction of the 16 ATA steam supply scheme
Reconstruction of the CHP plant with the conversion of boiler unit No. 9 to burn non-project fuel (g...
Setting up control systems and a dispatching system for autonomous boiler houses (11 units) in Chern...
Setting-up an automatic frequency control station for electric motors of network pumps with the inst...
Technical re-equipment of the automated control system for pumping units (ACS PU)
Technical re-equipment of the automatic control system (ACS) for the superheated steam temperature c...
Technical re-equipment of the raw water supply scheme for the ultrafiltration unit (UFU) at the CHP ...
Technical re-equipment of the wastewater treatment unit by applying the complex technology of membra...
Got questions?