Reconstruction of the CHP plant with the conversion of boiler unit No. 9 to burn non-project fuel (gas group coal)
CLIENT
Euro-Reconstruction LLC
YEARS OF IMPLEMENTATION
2023
TYPE OF WORKS
Installation works, equipment supply, software development, comprehensive testing and commissioning
Equipment used, specifics of works provided
According to the project, the following was implemented:
- installation of cold air pipelines from the BF to the mill inlet, equipping the hot and cold air pipelines with control valves to ensure that the temperature behind the mill is maintained at about 70°C in a wide range of fuel quality and load limits;
- supplying the transport air ramp with a pipeline of low-heated air taken after the first stage of the air heater with a control gate to ensure that dust is supplied to the burners both during operation and during MB shutdown, and the temperature of the air mixture in front of the burners is no more than 170°C, no more than 150°C in the case of a filled dust duct;
- replacement of dust ducts from dust feeders to burners with a smaller diameter to ensure the air mixture velocity in the dust ducts exceeds 25 m/s;
- replacement of burners.
Based on the software and hardware complex OVATION Emerson software and hardware complex, an automated control system was implemented:
- dust preparation;
- dust feeding;
- boiler load regulator.
To control the signs of violations of the normal operating mode, the dust system is equipped with control points for technological parameters:
- exceeding the maximum permissible temperature at any point of the dust system;
- exceeding the permissible temperature at the burner inlet (for example, due to malfunctioning of dust feeders, smoldering in mixers, clogged dust ducts, etc;)
- overloading of the mill;
- increase of pressure in the dust system to the design pressure of operation of explosive safety valves.
Installation works
Equipment supply
Commissioning works
Software development
Complex tests
Similar projects
Adjustable micropower drive for coal hoisting machine MPB 5x2x2
Adjustment of project documentation “DZF. Automatic pump control system 8NDV”
Automation of drying at 1, 3, 4 process lines at Centralized processing plant
Automation of the combustion safety system at the Centralized Processing Plant furnace unit No. 5 of...
CHP plant reconstruction with the conversion of boiler units No. 6, No. 7, No. 8 to burn non-designe...
Commissioning of five distribution devices for connecting frequency converters, including parameteri...
Construction of a water treatment plant at PJSC “POEZ-KERNEL GROUP” for the project impl...
Design and commisioning of the control and safety system for the GM-3 hydraulic unit
Emergencies early detection and people notification, in case of emergencies occurrence, system at th...
Implementation of the Coastal Pumping Station (CPS) NDV adjustable electric drive system at the CHP ...
Installation and commissioning of a set of equipment for water purification by reverse osmosis techn...
Modernization and development of electric drives and CNC control systems for metal-cutting and other...
Modernization of the automatic water level in boiler drums No. 1-4 regulation and control system
Modernization of the DZF unified control room
Modernization of the sewage pumping stations SPS-4 and SPS-7
Monitoring of the current load of the mill ball drive electric drives at mill No. 21115, inv. No. 12...
Oxygen and natural gas metering at the BRM based on Ergomera equipment
Reconstruction of the 16 ATA steam supply scheme
Reconstruction and automation of section No. 12, DSP
Reconstruction (technical upgrading) of the control and management system for the turbo-generator
Setting up control systems and a dispatching system for autonomous boiler houses (11 units) in Chern...
Setting-up an automatic frequency control station for electric motors of network pumps with the inst...
Technical re-equipment of the automated control system for pumping units (ACS PU)
Technical re-equipment of the automatic control system (ACS) for the superheated steam temperature c...
Technical re-equipment of the raw water supply scheme for the ultrafiltration unit (UFU) at the CHP ...
Technical re-equipment of the wastewater treatment unit by applying the complex technology of membra...
Got questions?
Want to know more about our products or services? Please, fill in the form, and our Customer Relations Manager will contact you as soon as possible!
Message us 