Project details

Pellets Production Workshop. Construction of the filtering and averaging of concentrate No. 1 housing. Replacement of VASA 459-200 FNR pumping units at the 0.00 mark on the 2nd technological line with FLSmidth units

CLIENT
Ferrexpo Poltava Mining
YEARS OF IMPLEMENTATION
2021
TYPE OF WORKS
Installation and commissioning

Equipment used, specifics of works provided

  1. Within the framework of the developed project, it is envisaged to improve the existing system of using pumping units by replacing the pumping units with a change in the control system and collecting information with the adaptation of the output data to the existing system to control the technological processes of the production line.

Installation works
Commissioning works