Modernization of st. #1 turbogenerator. Replacement of the electromagnetic exciter with a thyristor excitation system
CLIENT
CHPP
YEARS OF IMPLEMENTATION
2016—2018
TYPE OF WORKS
Modification of the design and estimate documentation, installation work, equipment supply, commissioning works
Equipment used, specifics of works provided
- Project development.
- Installation.
- Complex tests and commissioning of the excitation system based on a power transformer type TSZP-1250/6-U3 6.3/665V (PE “ELTIZ”) and thyristor excitation system type SVTG-1,3k/350-1ES2T2,5-UHL4 (LLC “RDE “PREOBRAZOVATEL-COMPLEX”).
Modification of the design and estimate documentation
Installation works
Equipment supply
Commissioning works
Similar projects
Complete preventive inspection, restorative maintenance (K(V)), and testing of the ССТП-3500-465-2,5...
Construction, installation, and commissioning works for the reconstruction of the first power unit w...
Development of an independent thyristor excitation system SNVTG-600-200-1.6-UHL4 for the project ...
Reconstruction of power unit No. 7 with a capacity of 800 MW. Reconstruction of the control system t...
Reconstruction of the excitation system of a 25 MW turbine generator (replacement of the VT-120-3000...
Replacement of the electromagnetic exciter of the turbine generator TV-60-2 and ARZ type POA with a ...
Replacement of the existing single-channel thyristor self-excitation system type STS-300-2000-2,5-UH...
Supply of thyristor self-excitation systems for hydrogenerators of SSGG-1250-460-2UHL4 type
Technical re-equipment of the st. #. 1 excitation system G-1 TVV-320 (thermal power plant (TPP)