Project details

Modernization of automatic regulation and control of the of the water level control system for boilers No. 1–4 drums

CLIENT
CHP
YEARS OF IMPLEMENTATION
2018—2020
TYPE OF WORKS
Design, installation, equipment supply, software development, comprehensive testing and commissioning

Equipment used, specifics of works provided

  1. Our enterprise was the first in Ukraine to use the flagship Schneider Electric Modicon M580 controllers with hot redundancy.
  2. Installation of an LDM control valve for feed water Dy 225 RV701, with medium parameters: T = 230 ⁰C, P = 230 kgf/cm2 on welded joints with a wall thickness of 24 mm; installation of a feedwater and superheated steam flow sensor; the layout and assembly of the control cabinet was carried out by the company’s specialists, based on Schneider Electric equipment.

Design
Installation works
Equipment supply
Software development
Complex tests
Commissioning works