Project details

Installation the lamps on columns along the crane routes of building 1 (Centralized Crane Shop)

CLIENT
Ferrexpo Poltava Mining
YEARS OF IMPLEMENTATION
2017
TYPE OF WORKS
Installation and commissioning

Equipment used, specifics of works provided

  1. Implementation of a modernization system for the overhead lighting of the pellet production workshop in the existing production facilities.
  2. Implementation of a project to replace outdated lighting fixtures with new LED ones.
  3. The work was complicated by a large number of works at height and high temperatures (sometimes over 70°C).

Installation works
Commissioning works