Project details

Development of a working project for the replacement of stationary control posts (PU) No. 6, 8, 9 of mills 800, 650 of the large-grade rolling shop with modular ones

CLIENT
PJSC "MK "Azovstal"
YEARS OF IMPLEMENTATION
2018—2019
TYPE OF WORKS
Design, supply of equipment, installation works

Equipment used, specifics of works provided

  1. Dismantling and installation work was completed in 15 days during the rolling mill shutdown.