Crushing and processing plant (DZF). Reconstruction of blowers at the flotation site of OPU-4

CLIENT
Ferrexpo Poltava Mining
YEARS OF IMPLEMENTATION
2017
TYPE OF WORKS
Construction, electrical installation, commissioning works

Equipment used, specifics of works provided

  1. Installation and commisioning of the Aerzen Delta blower GM 240S with a capacity of 3477 m³/h.
  2. Foundation arrangement, installation of frequency-driven control units, installation of cable routes, power and control cables, and comprehensive testing.
  3. The works were carried out in a short time, during a short shutdown of the process equipment.

Installation works
Commissioning works